Cloud Torque Global - Scheduled Maintenance – Hamilton Data Centre (Third-Party Facility) – Maintenance details
All systems operational
Scheduled Maintenance – Hamilton Data Centre (Third-Party Facility)
Completed
Scheduled for November 25, 2025 at 8:00 PM – November 26, 2025 at 2:00 AM
Affects
Datacentre - Hamilton
Under maintenance from 8:00 PM to 2:00 AM
Virtual Servers
Under maintenance from 8:00 PM to 2:00 AM
Web Servers
Under maintenance from 8:00 PM to 2:00 AM
Primary Transit
Under maintenance from 8:00 PM to 2:00 AM
Secondary Transit
Under maintenance from 8:00 PM to 2:00 AM
Voice Services
Under maintenance from 8:00 PM to 2:00 AM
Updates
Completed
November 26, 2025 at 2:00 AM
Completed
November 26, 2025 at 2:00 AM
Maintenance has completed successfully
In progress
November 25, 2025 at 8:00 PM
In progress
November 25, 2025 at 8:00 PM
Maintenance is now in progress
Planned
November 25, 2025 at 8:00 PM
Planned
November 25, 2025 at 8:00 PM
Our Hamilton Data Centre provider will be performing a scheduled maintenance window to upgrade the facility’s UPS hardware. This forms part of their ongoing program to improve reliability, redundancy, and long-term sustainability of the power infrastructure that supports the CloudTorque servers we colocate there.
Purpose of Maintenance: To upgrade the UPS hardware and enhance the stability and performance of the power systems within the facility that houses our equipment.
Customer Impact: The risk of service impact is low. No interruptions are expected, and the facility operator will be taking all necessary precautions to prevent disruption. However, there is a slightly elevated risk during the maintenance window.